Jurong Island Phase 3 (Area 3A)

 

The amalgamation of the southern islands off Singapore into one big petrochemical hub involves massive reclamation and ancillary concrete works. Just one of the many parcels, this project constitutes the construction of 3 bridges, roads, drains and soil improvement works. 

Managed by local industrial landlord Jurong Town Corporation and through a joint venture effort by Penta Ocean and Koon Construction, all bridge beam surfaces, decks, abutments, soffits and cupping beams to steel sheet piles were impregnated with Dry-Treat BHN IBTEO silane against corrosion.